| Pump station: |
2 screw conveyor, 800 mm, Tilt angle 33° Qmax 128 l/s |
| Emergency screening plant: |
1 bar-screen Bar - spacing 3 mm |
| Screening plant: |
2 bar - screen, 700 mm Bar spacing: 5 mm; Qmas=936 m3/h by 1 screenings wash presses integrated and bagging decive |
| Aerated grit chamber: |
2-line, each line, Grit chamber Cross selection 2,07 m² Volume 67,2 m³ T = 9 min per Qt Grit washer Qm= 12 l/s |
| Preliminaty clarifier: |
1-line, Wide 6,0 m; Lenght 18,60 m Water depht 2,35 m V=254 m³…….t = 0,49 h by Qt Longitudinal flowed, sludge scrapers |
| Biological basin: |
2-line, each line Aerob basin = 620 m³ Anix basin (denitrification) 2 Basins = 880 m³ Aerob basin (nitrification) = 1.325 m³ 162 pieces membrane diffusers Volume totale: Aerob basin 1.320 m³ Denitrification 1.760 m³ Nitrification 2.650 m³ Totale A+VD+VN = 5.730 m³ 2 Horizontal agitator Q = 16.990 m³/h Recirculation pumps 2 x Q = 120 l/s 4 compressor, each 300/720 Nm³/h, 19,3 kW |
| Final clarifier: |
4 basins, Lenght / Wide = 37,0/6,0 m Water depht = 4,80 m; V = 4.160 m³ Longitudinal flowed, chain&flight scrapers |
| Phosphorate Precipitation: |
Simultaneous precipitation |
| Quantity of row sludge: |
Row sludge 182 m³/d by 2.341 kg TS/d and 41 m³/d after primary sludge pretreatment |
| Pre-thickeners: |
1 pieces Diameter 7,00 ; Volume 1 x 234m³ Rabble rakes, sludge water separation |
| Secondary sludge pretreatment: |
Screencloth, Conditioning by Polyetectrolytes Q = 30 m³/h |
| Digestion chambers: |
1 piece Cylindrical tank D = 12,00 m; H = 12,70 m UsableVolume = 1.140 m³; Digestion time 45 days Circulation by biogas + pumps |
| Post thickeners: |
1 piece Diameter 7,00m; Volume 1 x 234m³ Rabble rakes |
| Gasometer: |
Cylindrical enclosure in steel construction Gas accumulator; Usable volume 490 m³; H = rd. 8,0 m |
| Gas flare plant: |
Capacity = 60 m³/h |
| Gas compressor station: |
2 Compressors |
Sludge dewatering: |
2 filter belt press, Conditioning by Polyetectrolytes, Q = 25 m³/h |
| Accumulo fanghi: |
Superficie: 220 m² Alimentato da coclee di trasporto |
| Impianto gas liquido: |
Serbatoio gas V = 25 m³ (interrato) con vaporizzazione |
| Trattamento aria: |
Chemical area treatment scrubber From meccanical and sludge treatment: 15.000 m³/h |
| Heating system plant: |
Heating system plant by 2 boiler plants each 350 kW thermal capacity by switching automatically for methane gas or biogas |
| Gas engine plant: |
1 peace each Ptot = 151 kW; Pel = 50 kW; Pt = 85 kW for propane and biogas |
| Deep well – industrial water: |
2 pieces of pumps, each 8 – 12 l/s |