Overview
Construction progress
Start of construction: October 1993
Completion: September 1999
Beginning of operation and function tests: October 1999 until December 1999
In operation since: 16. December 1999
Operational data
Yearly quantity of sewage: 1.510.000 m³/a
Sludge quantity: 980 Tons/a
Produced electrical energy: 400.000 kWh/a
Efficiency: BOD5 = 99%
COD = 95%
Ntot = 84%
Ptot = 92%